Tips: ALWAYS Pre-drill. Plan your boards out first so you do not end up with a 2" board as your last board. You may have to trim both your starter and end boards so both sides are even.

Step 1: If not installing molding, cut groove off of board.

Step 2: Pre-drill and then Screw and Plug edge of board as pictured above.

Step 3: Pre-drill through tongue and then and install SS Screw.

Step 4: Slide next board over tongue and pre-drill though tongue and then install SS Screw.

Step 5: Repeat Step 4 until last row.

Step 6: Trim last board as needed. Slide over tongue. Pre-drill and then Screw and Plug edge of board as pictured above.

Tongue and Grooved boards are for covered porches/decks, walls and ceilings. Do not install T&G on open decks.